Nov 05, 2021Retaining Wall Construction Project
The West Suburban YMCA is in the process of replacing the retaining walls in the front and back of the building. Below are a few details that our members and guests should be aware of in the coming weeks.
- Construction on the front retaining wall (adjacent to the track) will begin on Monday, November 8th at 8:00am.
- Our contractor will be using approximately 6 parking spaces in the "lower lot" for storing equipment during this part of the project.
- The work on the front wall will take approximately 4 weeks.
We will monitor the impact of the construction on our facility and communicate updates as needed.
The Y is becoming busier as the temperatures begin to drop, so we would like to remind you that there is additional parking available to members and guests behind the building.